Drawing of Stakeholder map
Project Management Dictionaries
Collaborative Online Mind Mapping:
  • #1 Mind Mapping Tool
  • Collaborate Anywhere
  • Stunning Presentations
  • Simple Project Management
  • Innovative Project Planning
  • Creative Problem Solving

What does As-Soon-as-Possible mean?

by | reviewed 2023-08-19

As-Soon-as-Possible

As-Soon-as-Possible (ASAP) is a scheduling approach commonly used in project management that emphasizes beginning activities at the earliest possible dates. This strategy is typically the default activity type in most project management systems. It prioritizes starting tasks as early as possible to minimize the risk of delays and ensure efficient project progress.
As-Soon-as-Possible - meaning and definition

What are the benefits of using ASAP?

The As-Soon-as-Possible (ASAP) scheduling method offers several advantages in project management, particularly regarding efficiency, risk mitigation, and proactive problem-solving. Some of the primary benefits of using the ASAP technique include the following:

Enhanced efficiency: The ASAP method promotes a smooth workflow and ensures efficient project progress by focusing on starting activities at the earliest possible dates. This approach helps prevent bottlenecks and idle time, enabling project teams to complete tasks promptly.

Risk mitigation: The ASAP scheduling technique minimizes the risk of delays by initiating tasks as soon as their prerequisites are met. This proactive approach helps keep the project on track and reduces the likelihood of scheduling issues or deadline extensions.

Proactive problem-solving: The ASAP method fosters a proactive mindset by encouraging project teams to address issues and challenges as they arise. This approach helps prevent minor issues from escalating into more significant, complex problems that could hinder project progress and negatively impact the project outcome.

Better resource allocation: With the ASAP technique, tasks start as soon as possible, so resources also start work as quickly as possible, potentially reducing downtime.

Improved communication: By focusing on starting tasks as soon as possible, the ASAP method promotes clear and consistent communication among project team members. This can result in better collaboration and coordination, ultimately leading to a more successful project outcome.

Greater adaptability: The ASAP scheduling approach encourages project managers to be agile and adaptable, allowing them to respond quickly to project requirements or scope changes. This flexibility can help project teams adapt to evolving circumstances and maintain momentum toward project completion.

Time and cost savings: By starting activities as early as possible, the ASAP method can lead to time and cost savings. Starting tasks without delay reduces the project's overall duration and associated costs.

In summary, using the As-Soon-as-Possible scheduling technique can provide numerous benefits for project management, including enhanced efficiency, risk mitigation, and proactive problem-solving. In addition, by focusing on initiating activities at the earliest possible dates, project managers can improve resource allocation, promote effective communication, and foster adaptability, all of which contribute to a successful project outcome.


See all project management words

Methodology specific dictionaries / glossaries